Where the Lopes Road Repair Stands as Cordelia Heads Into Winter

  • November 19, 2026

Drive south out of Cordelia on Lopes Road and you reach a gate about a quarter mile past Gold Hill Road. A second gate stands about half a mile north of Marshview Road. Fairfield put up both of them in mid-November 2023. The road between them has been closed since late winter storms in March 2023 brought down the hillside west of the road and broke a primary water line serving Benicia. This fall, Teichert Construction's crews started the repair behind those gates. How much of the hillside work gets done before the heavy rain will decide when the road reopens.

A frontage road that carried more than cars

Lopes Road runs along the west side of I-680, and it's also the bike link between Cordelia and Benicia. Caltrans's corridor planning describes a bicycle route that starts near Lake Herman Road in Benicia, follows Lopes Road north beside I-680 to the I-80/I-680 interchange, and continues into Fairfield. The Solano Transportation Authority's countywide bicycle plan lists a 2.1-mile Class II bike lane on Lopes Road from Cordelia Road to Gold Hill Road. That segment links to the bike lanes on Green Valley Road and Red Top Road.

The road also carries utilities. Fairfield's 30-inch potable water line and Benicia's 36-inch raw water line both run through the damaged section. In the spring of 2023, Benicia residents and businesses lived under a mandatory 20 percent conservation order while crews laid extra 12-inch temporary lines to restore the city's supply. Those temporary lines stay in place until the permanent repair is done. That explains why two cities share this project. Under the agreement between Fairfield and Benicia, Fairfield pays 75 percent of soft costs such as design and permitting, and Benicia pays 25 percent.

The order of the work sets the calendar

On July 21, 2026, the Fairfield City Council voted 6-0 to award Teichert Construction a $9.34 million contract. The job covers stabilizing the hillside, replacing the damaged Fairfield and Benicia water lines, rebuilding Lopes Road, and installing new striping and guardrails. The pieces have to go in a set order, and the city's updates show why.

The city's latest update puts slope stabilization ahead of pipeline replacement. In August, Hether told the council that after the utilities are repaired, crews "go back and start repairing the road." Soil testing in 2024 had already turned up signs of an earlier slide on the same hillside, estimated at more than 35 feet deep. So the first equipment on site is for deep soil mixing. In the city's October 28 update, it describes heavy rigs drilling large rotating augers deep into the slope and injecting a cement mixture. The augers blend the existing soil into solid, high-strength columns underground, and the slope is reinforced where it stands instead of being hauled away. Teichert is doing the work, and Dewberry Engineers is the project's geotechnical engineering team. In the city's words, finishing slope stabilization first "is essential to securing the hillside before the rainy season begins."

That makes the weather the one variable nobody controls. In August, Assistant Public Works Director Michael Hether told the council something the Daily Republic reported: "you don't want to start repairing the hillside and do the soil mixing and then just have everything undone by rain." At that point he expected the soil work to wait until spring. The city then moved it up, and by early November its position had changed. "The city intends to complete all slope stabilization activities along Lopes Road in advance of the upcoming wet season," Hether said in an email to the Daily Republic.

The city also gave the paper a backup plan in case the rain arrives first. It would keep monitoring ground movement, take winterization measures in unstable areas, and if needed bring in contractors for emergency temporary stabilization until the permanent work is finished. The statement followed a Solano County Board of Supervisors briefing on getting ready for a possible wet El Niño winter. At that briefing, county Office of Emergency Services manager Robyn Rains said that of the six previous El Niño winters, two had normal rainfall, two above normal and two below. The winter of 2022-23, which brought the hillside down, was not an El Niño season.

Two ways the city has described the finish line

On May 20, 2026, when the city got Caltrans's authorization to advertise for bids, it said it looked forward "to reopening Lopes Road in spring 2027." At the August council meeting, Councilwoman K. Patrice Williams asked "How far away are we from having a Lopes Road that we can drive on?" and said it is the issue she gets asked about most. Hether's answer, as the Daily Republic reported, was that the road "will not likely be fully repaired until late next year." At the same meeting the council approved a $247,500 contract amendment with Dewberry Engineers.

So the city has given spring 2027 as a reopening target and late 2027 as the likely date for full repair. For planning a commute or a weekend ride, spring 2027 is the earliest date to expect, and late 2027 is a fair outside estimate. Look at how the schedule has moved before. In October 2025 the city expected construction to start in spring 2026. In May 2026 it expected August. The October update said soil mixing was starting. Each date moved later, but each step after the funding was secured actually happened. Hether also told the council that delivery of parts on time would affect the schedule.

For cyclists, the next link is across the freeway

The gates have kept bikes and people on foot out of the closed section since 2023, so the Class II route between Cordelia and Benicia has had a gap for close to four years. The Benicia Bicycle Club has proposed a fix on the other side of I-680. At its year-end meeting on December 7, 2025, the club said it had contacted the new director of the Pacific Flyway Center about letting bikes through on Ramsey Road, on the east side of the freeway. In the club's words, Ramsey Road "would provide immediate bike passage to beloved Suisun Valley and surroundings."

That request ties the Lopes Road story to the other project taking shape at Cordelia's southern edge. The Pacific Flyway Center is being built in the Suisun Marsh east of I-680 and south of Cordelia Slough, off Ramsey Road, with California Waterfowl as its fiscal sponsor. Phase 1 is a 124-acre "Walk in the Marsh" with paths, boardwalks and visitor access. A later phase adds an education center. The Daily Republic reported the trails as 80 percent complete in June 2025. In the fall of 2025, when crews began flooding the ponds, the paper reported that benches, a shade structure and interactive signs were still to come and that the Walk was projected to open to the public in spring 2027.

If both projects keep to their published spring 2027 targets, the land on both sides of I-680 south of Cordelia changes in the same season. Lopes Road comes back on the west side and a public marsh walk opens on the east. Either one would add a destination to a Saturday ride or an afternoon walk out of 94534. Both would fit into the loops in our Cordelia weekend guide.

Where the updates land first

The city has kept a running log of every step since 2023 on its Lopes Road page, including drone footage of the damage from April 2023 and the full set of project plans. In August, Hether said the city planned an active outreach effort during construction and that construction news would post to that page. The page also has a subscribe link for email and text alerts. If you want an early read on spring 2027, watch for the update saying slope stabilization is finished and pipeline replacement has begun. Once the city posts that, the remaining work is the road itself.

At City 1st Realty, we're part of the Cordelia and Green Valley community, and projects like the Lopes Road repair are part of the conversation with our neighbors. If you want to talk about what's coming to the south end of Fairfield, or how it fits your own plans in the neighborhood, visit our Cordelia page and let's talk. Work with Us.

Work With Us

Our dedicated teams combined experience, familiarity with the market trends, and proven results, to ensure your transaction with us is a successful one. Call us today and experience a fresh new approach.

Follow Us on Instagram